INVESTMENT

 

 

 

In recent years, besides the main business line of consultant engineering services, PECC2 has made great efforts to seek investment opportunities, creating value added through the investment projects as well as more employment. All the PECC2 investment projects are selected carefully and aimed at the mini hydropower and renewable energy projects. With the advantages of professional consulting services, the PECC2 investment projects are regarded highly feasible.
Currently, the Government of Vietnam has paid special attention to promoting the development of renewable energy sources to ensure energy security, mitigate climate change and protect the environment by issuing series of policies to support the development of wind power, biomass, solar power, etc.
With the approval by Vietnam Electricity (EVN) - the biggest shareholder of PECC2, over the past two years, in addition to the expansion of business operation of the Company, PECC2 has actively invested in Thac Ba 2 Hydropower Plant Project, Solar Power Project in Vinh Tan Complex, Tan Thuan Wind Power Project and Son My 3 Solar Power Project, etc..

TYPICAL INVESTMENT PROJECTS

•  Place: Han Da Commune, Yen Binh Dist., Yen Bai Provincei
•  Designed capacity: 21 MW
•  Output: 52 million kWh/year
•  Planned schedule:
-    Commencement: 2020
-    Completion: 2022

•    Place: Vinh Tan Power Complex, Tuy Phong Dist., Binh Thuan Province
•    Designed Capacity: 5 MWp
•    Output: 7.76 Million kWh/year
•    Commencement: 2018
•    Completion: 2019

•    Owner: PECC2
•    Place: Son My Commune, Ham Tan Dist., Binh Thuan Province
•    Designed Capacity: 50 MWp
•    Output: about 78.7 million kWh/year.
•    Commencement: 2018
•    Completion: 2019

•    Place: Tan Thuan Commune, Dam Doi Dist., Ca Mau Province
•    Designed Capacity: 75 MW
•    Output:    220 million kWh/year
•    Planned schedule: 
-    Commencement: 2019
-    Completion: 2021

•    Place: Ba Ria – Vung Tau
•    Designed Capacity: 1200 - 1500 MW
-    Output: About 9 – 9.9 billion kWh/year
-    Planned schedule: Being implemented

•    Place: Nui To Commune, Tri Ton District, An Giang Province 
•    Project Parameter:
-    Designed Capacity: 2x30MW
-    Output: About 390 million kWh/year
•    Planned schedule: 
-    Commencement: 2022
-    Completion: 2023

•    Place: Thuan An Ward, Long My Town, Hau Giang Provine
•    Project Parameters:
-    Designed Capacity: 20MW
-    Output: About 130 million kWh/year
•    Planned Schedule:
-    Commencement Quarter III 2021
-    Completion: 2023  

•    Place: Luu Nghiep Anh Commune, Tra Cu District, Tra Vinh Province
•    Project Parameters:
-    Designed Capacity: 25MW
-    Output: About  162,5million kWh/year
•    Planned Schedule: 
-    Commencement : Quater IV 2021
-    Completion: 2023