Vinh Tan 2 Thermal Power Plant

  • Location:
    Vinh Tan commune, Tuy Phong district, Binh Thuan province
  • Total investment:
    23,927 billion VND (1,104 billion USD)
  • Designed Capacity:
    1 x 600 MW
  • Commencement:
    4/2016
  • Status:
    Completed in December 2019
  • Investor:
    EVN

EPC contractor: Doosan contractor complex (Korea) - Mitsubishi Corporation (Japan) - Thai Binh Duong Group Joint Stock Company, Power Construction Consulting Joint Stock Company 2

The extension of Vinh Tan 4 thermal power plant is one of the urgent projects contributing to solving the electricity shortage for the South after 2020 of the Government, invested by EVN, EVNGENCO 3 is implementing the Project Management Consultancy. The project is represented by the Management Board of Vinh Tan Thermal Power Project, with a total investment of over VND 23,000 billion, a total installed capacity of 600 MW (1x600 MW), an electricity output of about 3.6 billion kWh/year. This project is of great significance, marking a new development step of Vietnam's electricity industry with some outstanding features such as the first large-scale use of coal using supercritical steam parameters built in Vietnam. Vietnam, the localization rate is high, the first large-scale thermal power plant project is chaired by a Vietnamese consultant.

Chia sẻ: